Notes
Field notes: the parcel that passed every layer except the easement cutting it in half

A parcel came through screening a few weeks back that I keep thinking about. 220 acres, slope under 4% across almost the whole footprint, south-facing, pasture for decades so no clearing fight, outside the 100-year floodplain by a comfortable margin. On paper it was the kind of parcel you circle twice and move straight to outreach.
Then someone pulled the recorded instruments and found a 24-inch interstate gas line running corner to corner, with a 75-foot easement on either side that nobody in the GIS stack had flagged, because nobody's GIS stack flags it. Slope maps don't know about buried pipe. Land cover classifiers see grass whether or not there's a transmission corridor under it. Flood layers are flood layers. The easement doesn't show up until a title company or a plat search turns it up, and by then the parcel has already eaten a chunk of someone's week.
What the easement did to the parcel was worse than the acreage loss suggests. It didn't take a tidy 150-foot strip off one edge. It cut diagonally, which meant the two remaining pieces were a 90-acre wedge and a 110-acre wedge, neither one square enough to rack panels efficiently, and both now carrying a new perimeter-to-area ratio that pushed fencing and access-road cost per megawatt somewhere nobody wanted to go. A parcel that looked like a single clean build became two marginal ones, and the setback math alone ate most of the margin that made it worth pursuing in the first place.
This is the part of the job that physical screening can't do for you and isn't pretending to. Slope, aspect, size, shape, land cover, water, flood, these are things you can read off imagery and elevation models at scale, across a whole county, without anyone leaving the office. An easement is a recorded legal instrument. It lives in a courthouse or a title plant, not in a multispectral band. No amount of resolution fixes that, because resolution was never the problem.
What's changed, talking to a few people doing this work, is where in the process the easement question gets asked. It used to come up after a site visit, sometimes after a letter of intent. Now the land managers I talk to want it earlier, right after physical screening narrows a region down to the handful of parcels worth the title search. That ordering matters more than it sounds like it should. Running title on every parcel in a 40,000-acre study area is a waste of a paralegal's month. Running it on the dozen parcels that already cleared slope, aspect, and flood is a normal Tuesday.
That's the value of getting the physical pass/fail answer first: it shrinks the pile you're paying someone to dig through at the courthouse. A regional screening pass, the kind that comes back as a parcel table instead of a stack of individual reports, tells you which 12 parcels out of 400 are worth that next call. It won't catch the pipeline, the transmission corridor, or the mineral rights carve-out sitting in a 1987 deed. Nothing short of a title search catches those. But it keeps you from spending title-search money on a parcel that was going to fail on slope anyway.
The 220-acre parcel is still in the pipeline, just not as one parcel anymore. The 110-acre wedge is being reworked as a smaller standalone project. The 90-acre piece is probably going back on the shelf until someone needs exactly that size. Not a dramatic ending, just the ordinary attrition of land work, one easement at a time.
If your study area has a few hundred parcels and you haven't run the slope-aspect-cover-flood pass on all of them yet, that's the cheap step to take before the expensive one.